Section Ill. OPERATION UNDER USUAL CONDITIONS
2-6. OPERATING PROCEDURES. The following infor-
2-5. INITIAL ADJUSTMENTS AND DAILY CHECKS.
mation applies to all operating procedures; however,
Perform before (B) PMCS (p 2-4). Refer to symptom
additional procedures may be required when operating
index (p 3-2) for troubleshooting malfunctions.
from a nonmoving vehicle or trailer. (See TM 3-1040-
255-10 for using the M2 smoke generator mount and
M3 fog oil drum mount on vehicles and trailers.)
a. Positioning Equipment for Operation.
WARNING
Flames, hot gases, or hot fog oil may shoot out from smoke outlet nozzles up to 24 hours after
operation. Use two people at nozzle end, one on each side, to lift and carry a hot smoke
generator.
a. Place smoke generator (1) on a level surface for operation. To carry smoke generator, pull pins (2) on four
chain assemblies. Extend handles (3) and resecure with pins.
b. After emplacement, pull pins, push handles in, and resecure with pins.